Lab 5. Resource Planning for Project Execution in MS Project

Lecture



Lab 5: Resource Planning for Project Execution in MS Project

Objectives:

  • Learn to plan resources for project execution using MS Project.
  • Master the program's core functions for managing project resources, tasks, and schedules.

Steps for completing the lab:

  1. Creating a new project:

    • Open MS Project.
    • Create a new project by selecting «File» → «New» → «New Project».
    • Set the project start date in the «Project» → «Properties» section.
  2. Defining the project tasks:

    • Enter the list of tasks in the «Tasks» table. Include task names, durations, and dependencies (if any).
    • Use the «Task Name», «Duration», «Start», and «Finish» columns to organize the tasks.
  3. Creating resources:

    • Go to the «Resources» view (View → Resource Sheet).
    • Enter information about the resources needed for the project:
      • Resource name: Name (e.g., «Developer», «Tester»).
      • Resource type: Work, Material, Cost.
      • Workload: Specify the number of hours the resource will be available per week.
      • Resource cost: If required, specify the hourly rate or fixed cost.
  4. Assigning resources to tasks:

    • Return to the «Tasks» view (Task View).
    • Select the task to which you want to assign a resource.
    • On the «Task» tab, select «Assign Resource» (Assign Resources).
    • In the window that opens, select the resource and click «Assign».
  5. Setting dependencies between tasks:

    • Set up dependencies between tasks if one task depends on another.
    • To do this, select the task and enter the number of the preceding task in the «Predecessors» field (Predecessors).
  6. Optimizing resource utilization:

    • Go to the «Resource Graph» view (Resource Graph) to analyze resource workload.
    • If resource utilization exceeds 100%, consider redistributing tasks or adding additional resources.
  7. Building a Gantt chart:

    • Go to the «Gantt Chart» view (Gantt Chart) to visualize the tasks and their timelines.
    • Make sure all tasks are displayed correctly and show their dependencies.
  8. Saving the project:

    • Save the project by selecting «File» → «Save As» and choose a location to save the file.
  9. Project report:

    • Go to the «Reports» section (Reports) to create reports on resources and tasks.
    • Select the desired reports and configure their display.

Assignments to complete:

  • Create a project consisting of 5–10 tasks with various dependencies and resources.
  • Assign resources to each task and analyze the workload.
  • Optimize resource utilization if necessary.
  • Prepare and print a resource report.

Results of the lab:

Upon completing the lab, you should:

  • Master the core resource-planning functions in MS Project.
  • Be able to assign resources to tasks and analyze their workload.
  • Learn to use a Gantt chart to visualize the project.

Comments

To leave a comment

If you have any suggestion, idea, thanks or comment, feel free to write. We really value feedback and are glad to hear your opinion.
To reply

Lectures and tutorial on "System analysis (systems philosophy, systems theory)"

Terms: System analysis (systems philosophy, systems theory)